Initial purchase was made in August 2022, however a deal was agreed that the current tenants could remain in the building whilst they waited for their new premises to be built. a 9 month free rental agreement was made.
August 2022
May 2023
Official Purchase
Background works took place on a new scheme for this development and plans for the building
Planning Submitted #1
August 2023
September 2023
Planning Granted #1
Permitted development granted for 21 apartments in September
Planning Submitted #2
Additional planning has been submitted to expand the building from 2 storeys to include 2 more floors, resulting in a total of 4 storeys at the front and 3 more on the side elevation, bringing the total to 5 floors.