Purchased in May 2024 with planning already in place and no conditions, work on the project began in June 2024 with an estimated completion in October. By June, the site was cleared, followed by drainage installation. Stud work and wall construction started in mid-July, with first-fix plumbing completed by the end of the month. Still on track for October 2024 completion.
Dominion House Adam Court
POA - Price on Application. Call for further information on this development.
- 8 Bedrooms
- 123Sqm
- 8 Bathrooms
Property Timeline
Purchased
May 2024
May 2024
Planning
Planning was already in place for Adam Court due to plans with previous sold developments within Adam Court. No outstanding conditions.
Works Commenced
First-fix electrics are underway, and ceilings and walls will be closed up by August 12th. Plastering begins on August 13th, with kitchen installations set for August 23rd, and carpenters and painters scheduled for the following week. Works continue.
June 2024
September 2024
Works Continue
Works have remained on track at our Adam Court development for completion October 2024.